A large hyperscale data centre project on a 350-acre site in Ireland for a large social media company. CLN 2 formed part of a series of schemes on this project that blu-3 managed to secure after greatly impressing the client with the quality of work carried out.
Location
Ireland
Client
Confidential
Main Contractor
Mace
Value
£12M
Second phase of enabling works for the main development of CLN2 Building
Project Challenges & Solutions:
- Site exhibited difficult ground  and weather conditionsÂ
- On site logistics with main development buildÂ
- Reactive works to support main development scheduleÂ
Scope:
- Extension of previous enabling works to support the main  development of Building CLN2 (Earthworks, asphalt road  construction, services)Â
- New access road 900m with full infrastructure and servicesÂ
- Widening and re-construction of local road adjoining site to support post development traffic usageÂ
- 145,000m3 of construction arisings, hauled and disposed to local licensed landfill facilitiesÂ