The A27 highways infrastructure project posed significant difficulties due to a stringent timetable to ensure the scheme's remaining works could be complete on time. The blu-3 team operated extremely efficiently to ensure all work was completed in under a month.
Location
A27 between
Arundel & Worthing
Client
Highways England
Main Contractor
Aone+
Value
£1,200,000
Project Challenges & Solutions:
- The project had a very strict timescale
- The works needed to be complete in time for the large-scale resurfacing works. These works were programmed for the summer of 2019, leaving only one month to complete the project
Scope:
- Widening the existing 1km footway by 700mm, creating more room for cyclists and pedestrians
- Installation of tactile on all existing crossings
- Additional works including the installation of over 30 new signs, 200m3 of concrete and 3000m2 of tarmac