An Iconic Project

A27 Cycleway

The A27 highways infrastructure project posed significant difficulties due to a stringent timetable to ensure the scheme's remaining works could be complete on time. The blu-3 team operated extremely efficiently to ensure all work was completed in under a month.

Location

A27 between Arundel & Worthing

Client

Highways England

Main Contractor

Aone+

Value

£1,200,000

Project Challenges & Solutions:

  • The project had a very strict timescale
  • The works needed to be complete in time for the large-scale resurfacing works. These works were programmed for the summer of 2019, leaving only one month to complete the project

Scope:

  • Widening the existing 1km footway by 700mm, creating more room for cyclists and pedestrians
  • Installation of tactile on all existing crossings
  • Additional works including the installation of over 30 new signs, 200m3 of concrete and 3000m2 of tarmac